Oakland, CA

Bridge Point Oakland

The project consisted of historic preservation and the construction of a new single-story concrete tilt-up warehouse/distribution facility. It involved site remediation, demolition of eight existing buildings, and salvaging/shoring a historic brick facade for incorporation into the new design.

Oltmans’ scope also includes site remediation and the demolition of eight (8) existing buildings, while salvaging and shoring a historic brick facade which will be incorporated into the new building design.

Ground Improvements - EPA & DTSC Oversight

During activities generating dust, all on-site personnel had to be HAZWOPER trained. Due to soil composition, clean corridors were built for underground wet and dry utilities. A Vapor Intrusion Mitigation System (VIMS) was installed, and the existing Groundwater Extraction Treatment System (GETS) was relocated and maintained during construction. A site-wide cap was installed to contain dust, with above-ground planters ensuring cap protection across all landscape areas.