Henderson, NV

Haas Automation Henderson, NV

Preconstruction and construction of a 2.4M s.f., three-building, 277-acre site development project in Henderson, NV.

Preconstruction and construction of a 2.4M s.f., three-building, 277-acre site development project in Henderson, NV.

Ph 1 Mass Grading & Underground Infrastructure

Completed under budget and on time, Phase I encompassed over two (2) years of preconstruction coordination resulting in 277-acres of mass grading, 10,000 cubic yards of concrete poured, and 57,000 lineal feet of underground utility infrastructure installed (excluding electrical). This was performed in preparation for the construction of three (3) industrial buildings totaling roughly 2.4 million square feet, as well as two (2) trucker’s lounges which will be located North of Via Nobila, our newly-constructed, public street.

  • 20 megawatts of power allocated for Phase I and II properties
  • Over one million cubic yards of soil transported for Phase I, elevating the site and three building pads
  • Multiple value engineering design options provided throughout preconstruction period, along with perpetual project schedule and buyout schedule updates

Offsites Summary

  • Construction of Larson Lane including: demolition of existing asphalt paving, earthwork,sewer, water, storm drain, street lighting as well as activity coordination with natural gas (self-performed by SW Gas). Also includes curb & gutter,asphalt paving / walking trail, signage & striping, underground infrastructure for a future traffic signal as well as future landscaping (will be completed during this next phase)
  • Partial construction of Via Inspirada including: earthwork, street lighting, curb &gutter, asphalt paving / walking trail, signage & striping, new city kiosk signage as well as activity coordination with natural gas (self-performed by SW Gas) & Cox Communication
  • Construction of Via Nobila including: earthwork, sewer, storm drain, water, street lighting,curb & gutter, asphalt paving / walking trail, NVE coordination &installation to bring 8 MW below Via Nobila stubbed over to Phase II property